LIGHT RAIL TRANSIT LINE 3 (LRT 3)
⚲ Malaysia
Delay and Quantum Claims and Quantity Surveying Services
System Work Package Contractors, Project Development Partner (PDP), and Subcontractor
2014-2024
A 37km light rail line connecting the Greater Klang Valley urban area with 26 stations that included viaduct, station, and associated works. Prepared consolidated extension of time and loss and expense claim, including prolongation costs, against the main contractor. Carried out training for the client’s project team.
On another package, Rimkus formed part of the claim consultant’s team fully retained by the PDP appointed by the government of Malaysia to manage, execute, and complete the overall project. Carrying out multi-tier contract administrations, advising on claims particularly on variations, internal reporting, and co-ordination with PDP project teams.
Further provided quantity surveying tasks for the internal fit-out works to the elevated section V2, including preparation of monthly progress claims, conducting site valuations, assessing subcontractor tenders, managing subcontract awards, and evaluating subcontractor progress claims.